My magic URL for upcoming data management releases points into Savannah.

We usually create a 'patch' (i.e. release) when we have a draft idea of what should
go into a release. For example FTS 2.2.3 and GFAL 1.11.13 are created with all the
bugs attached that we intend to implement by the release date.

The first noteworthy state is 'Ready for certification', when the developers have
finished their work and there are already RPMs created. At this point we usually
upload the packages into our Release Candidate repository for the convenience of
early testers.

The next noteworthy state is 'Certified', when the release has passed all regression
tests and the new features seem to be working.

After this state there is a few weeks of testing (i.e. waiting if there is any unexpected
behaviour) in the pre-production testbed (PPS) and then comes the gLite release.